Rules and documents

What the permit path cites

35 documents · read up to 2026-11-22 · each linked to the publisher’s official text

The regulatory path on each place page, the site brief and the assistant all draw on this list. Excerpts are short quotations of the clauses the app relies on: thresholds, who must do what, and published durations. The official text governs; nothing here is legal advice or a view on how an application would go.

Power plant approval (AUC)

Bulletin 2025-14: Amended Rule 007: Facility Applications

Sets a seven-year ceiling from initial approval to the end of construction for power plants and storage, with a new application needed after it expires.

AUC Bulletin 2025-14Alberta Utilities CommissionIn force 2025-11-06 (the amended rule it announces)Version 2025-10-06Read 2026-11-10

  • Appendix, Timelines to construct (resulting change)The upper limit the AUC will grant for a power plant application, absent unusual or extraordinary circumstances, is seven years from the date of initial approval to the date to complete construction.
  • Appendix, Timelines to construct (resulting change)After that seven-year initial period to construct expires, applicants must file a new application.
  • Appendix, Timelines to construct (resulting change)Facilities that are not expected to require seven years to construct should continue to put forward their best estimate and the AUC will consider the initial period to construct as part of its consideration of that application (e.g., the AUC will not automatically grant a blanket seven-year approval period for a five-megawatt power plant).

Seven years is a ceiling, not a default: each application still proposes its own completion date.

Decision 30732-D01-2026: Synapse Data Center Power Plant Project

The AUC denied a 1,400 MW gas plant at Olds because it was too close to the community, citing over 700 residences within 800 m.

AUC Decision 30732-D01-2026Alberta Utilities CommissionIn force 2026-08-17 (application denied)Read 2026-11-10

  • ¶2In this decision, the Alberta Utilities Commission denies Synapse’s power plant application. The Commission finds that the project is too close to the surrounding community, and Synapse failed to demonstrate any compelling justification for selecting that location.
  • ¶28The project site boundary is approximately 30 metres from the edge of the first row of properties across a residential road. Synapse stated that there are over 700 residences within 800 metres of the proposed project.
  • ¶36Synapse indicated that more than 700 residences were identified within the consultation radius (800 metres) and that more than 1,000 residences were within the notification radius (2,000 metres).

Denial rests on siting, not on consultation (¶37).

Hydro and Electric Energy Act

No one may build or operate a power plant without an AUC approval order.

RSA 2000 c H-16, s. 11Legislature of Alberta; approvals by the AUCIn force RSA 2000Version consolidation current as of 2024-03-06Read 2026-11-10

  • s. 11No person shall construct or operate a power plant unless the Commission, by order, has approved the construction and operation of the power plant.
  • s. 1(1)(k)“power plant” means the facilities for the generation and gathering of electric energy from any source;

Hydro and Electric Energy Regulation

Exempts small power plants under 1 MW at a site from the approval requirement, on conditions, and sets the isolated-system exception under 10 MW.

Alta Reg 32/2024Government of AlbertaIn force 2024-03-06Version as filed 2024-03-05Read 2026-11-10

  • s. 3(1)(b)“small power plant” means a power plant (i) consisting of all of the generating units that are or will be located at a site, and (ii) that has or will have a total capability of less than one megawatt.
  • s. 3(2)Subject to subsection (3), unless the Commission directs otherwise, a small power plant or small energy storage facility that is or is intended to be connected to a transmission line or electric distribution system is excluded from the application of sections 11, 13.01 and 18 of the Act.
  • s. 4(3)(a)(3) Subsection (2) does not apply unless (a) either (i) the total generating capability of the power plant, (ii) the total storage capability of the energy storage facility, or (iii) where a power plant and an energy storage facility are located on a common site, the combined total generating and storage capability including any replacement or addition, as the case may be, is less than 10 megawatts, and

Replaced AR 409/83. The under-1 MW exclusion holds only if no person is directly and adversely affected, there is no adverse environmental effect and Rule 012 is met (s. 3(3)); the under-10 MW isolated-unit exception is for the owner of a distribution system serving an isolated area, not a private developer (s. 4).

Rule 007: Facility Applications

How to apply to the AUC for a power plant: the under-1 MW exemption, the checklist route from 1 to under 10 MW, full applications at 10 MW and over, participant involvement radii and the processing timelines.

AUC Rule 007Alberta Utilities CommissionIn force 2025-11-06Version approved 2025-09-25Read 2026-11-10

  • 4.1.2 Power plants less than one megawattIf the power plant is less than one MW, the owner may proceed without filing an application if the requirements of subsection 3(3) of the Hydro and Electric Energy Regulation are met.
  • 4.2 Checklist applications (first bullet)Is or will be located at a site that will have a total capability of one MW or greater and less than 10 MW, regardless of whether the energy generated is solely for its own use or for export to the Alberta Interconnected Electric System;
  • 4.2 Checklist applicationsThe Commission will assess eligibility for an application to be filed as a checklist application and will issue a decision within five business days of receiving a properly completed checklist application.
  • 4.2 Checklist applications (sidebar)An application to construct and operate a power plant that is 10 MW or greater is not eligible for the checklist application process and must include the requirements corresponding to the power plant type (e.g., wind, solar, thermal).
  • Table 4.7 (thermal power plants, row read across)≥ 10 MW urban or rural 2,000 metres 800 metres
  • Appendix A1, 6.3 Engagement with local municipal jurisdictionsFor any power plant and energy storage facility application, the applicant must provide the Municipal Engagement Form to the applicable municipality to complete for a minimum of 30 days before the application is filed.
  • Table 3.1 (categories 1 to 5, rows read across)Record development timeline 5 business days* 35 days 90 days 120 days 205 days ... Decision writing timeline 15 days 20 days 30 days 75 days 90 days
  • Table 3.1 footnoteThis is the only performance standard based on business days; all other performance standards are based on calendar days.
  • 5.1 Initial period to constructFrom the power plant’s initial approval date, applicants will have up to seven years to finish construction, absent unusual or extraordinary circumstances.

Every claim the app makes was found in this edition. The under-1 MW route depends on the Hydro and Electric Energy Regulation s. 3(3) conditions; the checklist route also needs no direct and adverse effect on people or the environment and Rule 012 compliance. Radii are measured from the edge of the project boundary. Table 3.1 figures are performance targets (record development 90% or 80% of the time, decisions 100%), and only category 1 is in business days.

Environmental approval and assessment

Activities Designation Regulation

Under the Environmental Protection and Enhancement Act, a thermal power plant over 1 MW needs an approval, except emergency-only backup units not connected to the distribution system up to 50 MW.

Alta Reg 276/2003Government of AlbertaIn force 2003Version consolidated to Alta Reg 177/2026, current as of 2026-07-03Read 2026-11-10

  • s. 5(1)The activities listed in Schedule 1 are designated as activities in respect of which an approval is required.
  • Sch. 1, Div. 2, Part 9, cl. (i)Part 9: Power Plants (i) the construction, operation or reclamation of a power plant;
  • s. 2(2)(vv)“power plant” means a plant that produces steam or thermal electrical power and has a rated production output of greater than one megawatt under peak load, but does not include [...] (iii) a backup power generating system that (A) is only used to provide power to a facility when the facility’s principal source of power is interrupted, (B) is not connected to the electric distribution system, and (C) has a total rated production output of no more than 50 megawatts under peak load;

Environmental Assessment (Mandatory and Exempted Activities) Regulation

Lists the projects that must do an environmental impact assessment; thermal plants are on it only when they burn non-gaseous fuel at 100 MW or more.

Alta Reg 111/93Government of AlbertaIn force 1993-09-01Version consolidated to Alta Reg 272/2025, current as of 2025-12-03Read 2026-11-10

  • s. 1A proposed activity listed in Schedule 1 that has not been commenced is designated as a mandatory activity for the purposes of the Act.
  • Sch. 1, cl. (k)(k) a thermal electrical power generating plant that uses non-gaseous fuel and has a capacity of 100 megawatts or greater;
  • Sch. 2, cl. (i)(i) the construction, operation or reclamation of a backup power generating system that is only used to provide power to a facility when the facility’s principal source of power is interrupted and that is not connected to the electric distribution system.

Gas-fired plants are not on the mandatory list; the Director’s power to require an assessment anyway sits in Part 2, Division 1 of the Environmental Protection and Enhancement Act (ss. 43 to 47), quoted under that Act in this library.

Environmental Protection and Enhancement Act, Part 2, Division 1: Environmental Assessment Process

Lets the Director (or any Director, by referral) require an environmental assessment of an activity that is not on the mandatory list, decide on a screening report whether a full environmental impact assessment report is needed, and lets the Minister order one regardless.

RSA 2000 c E-12, ss. 40 to 59 and 63Legislature of AlbertaIn force RSA 2000 (first enacted as SA 1992 c E-13.3)Version consolidation current as of 2026-07-02Read 2026-11-10

  • s. 43Where the Director is of the opinion that the potential environmental impacts of a proposed activity warrant further consideration under the environmental assessment process, the Director may by notice in writing to the proponent advise the proponent that the proposed activity must be dealt with under section 44.
  • s. 44(1)(b)(b) if the proposed activity is not a mandatory activity, (i) make a decision that the potential environmental impacts of the proposed activity warrant further consideration under the environmental assessment process and require that further assessment of the proposed activity be undertaken, or (ii) make a decision that further assessment of the proposed activity is not required [...]
  • s. 44(3)In making a decision under subsection (1)(b), the Director shall consider the following: (a) the location, size and nature of the proposed activity; (b) the complexity of the proposed activity and the technology to be employed in it; (c) any concerns in respect of the proposed activity that have been expressed by the public of which the Director is aware; (d) the presence of other similar activities in the same general area; [...]
  • s. 45(4)Where the Director decides under subsection (1) that preparation of an environmental impact assessment report is required, the Director shall by order in writing direct the proponent to prepare and submit the report in accordance with this Division.
  • s. 47If the Minister is of the opinion that an environmental impact assessment report is necessary because of the nature of a proposed activity, the Minister may by order in writing direct the proponent to prepare and submit the report in accordance with this Division, notwithstanding that (a) the Director has not ordered an environmental impact assessment report, or [...]
  • s. 63 (Part 2, Division 2)Unless the regulations provide otherwise, the Director may not issue an approval or registration unless the Director is of the opinion that Division 1, if applicable, has been complied with.

For an activity that is not mandatory the route is: referral by any Director (s. 41), a Director’s notice (s. 43) or the proponent’s own consultation brings it to the designated Director, who decides whether further assessment is needed (s. 44(1)(b)); if it is, the Director prepares a screening report and decides whether a full report is needed (s. 45(1)). Directly affected persons have 30 days after notice of a further-assessment decision to file a statement of concern (s. 44(6)), and no decision under s. 45(1)(b) is made before that period ends (s. 46). Division 1 itself sets no time limit for the Director’s decisions; the regulations it refers to were not read for this library.

Noise

Rule 012: Noise Control

Permissible sound levels at dwellings near a facility: the nighttime basic sound level by proximity category and dwelling density, the daytime adjustment, the assumed ambient level and the 1.5 km receptor distance.

AUC Rule 012Alberta Utilities CommissionIn force 2026-04-17Version amendments approved 2026-04-15Read 2026-11-10

  • Table 1 (rows read across; columns 1 to 8, 9 to 160, 161 to 400, 401 to 1,000, over 1,000 dwellings per quarter section)Category 1 40 43 46 48 53 Category 2 45 48 51 51 53 Category 3 50 53 56 56 56
  • Table 1 note (1)Category 1—dwelling(s) distance is more than or equal to 500 metres (m) from heavily travelled roads or rail lines and not subject to frequent aircraft flyovers.
  • Table 1 note (4)Density per quarter section — refers to the number of dwellings within an area defined by a 451-metre radius, with the affected dwelling at the centre.
  • 2.1(8)The daytime adjustment is determined by adding 10 dBA to the nighttime basic sound level.
  • 2.1(9)(a)The assumed nighttime ambient sound level is five dBA less than the applicable basic sound level.
  • 1.3 Compliance (boxed text)A noise receptor is any dwelling located within 1.5 km of the facility property boundary. If there is no dwelling within 1.5 km, a noise receptor is any point at 1.5 km from the facility property boundary.

The app measures receptors from the site point; the rule measures 1.5 km from the facility property boundary.

Water

Approved Water Management Plan for the South Saskatchewan River Basin (Alberta)

The 2006 plan that stopped new water allocation applications in the Bow, Oldman and South Saskatchewan sub-basins pending a Crown reservation.

SSRB Approved Water Management Plan, 2006Alberta EnvironmentIn force 2006-08 (approved)Read 2026-11-10

  • s. 1.1The plan applies to all of the named rivers, their tributaries and all natural surface water with hydrological connection to the named rivers and tributaries. Groundwater that readily flows naturally under the ground to these surface water bodies is also considered surface water.
  • s. 2.1That AENV stop accepting applications for new water allocations in these sub-basins until the Minister of Environment specifies, through a Crown Reservation, how water not currently allocated is to be used.
  • s. 2.2[...] an allocation volume of approximately 600,000 dam3 (cubic decameters) be considered the initial total allocation target. When allocations reach 550,000 dam3, a temporary closure to applications to permit a review of the aquatic environment and allocations should be undertaken.
  • s. 2.7.1The Director (as designated under the Water Act) is hereby authorized to consider applications to transfer water allocations under licences in the SSRB in Alberta, subject to sections 81, 82 and 83 of the Water Act.
  • s. 2.7.2The Director is hereby authorized to withhold up to 10 per cent of an allocation of water under a licence that is being transferred, if the Director is of the opinion that withholding water is in the public interest to protect the aquatic environment or to implement a Water Conservation Objective.
  • s. 5 (Glossary, Groundwater)Groundwater that is in an aquifer that readily (drawdown cone for a well intersects a surface water body) flows naturally under the ground to surface water bodies is considered surface water for licencing purposes in Alberta.
  • Appendix DThe planning process focused on surface water issues. Groundwater that is not hydraulically connected to surface water is not considered in this plan.

Bow, Oldman and South Saskatchewan River Basin Water Allocation Order

Reserves all water not allocated in 2007 in the Bow, Oldman and South Saskatchewan basins, defined as the rivers, their tributaries and the groundwater naturally flowing to and from them, and lets the Director license reserved water only for listed purposes; transfers of existing licences are not affected.

Alta Reg 171/2007Minister responsible for the Water ActIn force 2007-08 (filing date not confirmed)Version as filed; no amendmentsRead 2026-11-10

  • s. 1(b)“Bow River Basin” means the Bow River and its tributaries and the water below the ground naturally flowing to and from the Bow River and its tributaries, within Alberta;
  • s. 2All the water in the Bow River Basin, Oldman River Basin and South Saskatchewan River Basin that is not, on the date this Order is filed under the Regulations Act, allocated under a licence or registration or specified in a preliminary certificate is reserved.
  • s. 3Water reserved under section 2 may be allocated by the Director.
  • s. 4(1)The Director may issue licences with respect to the Bow River Basin in accordance with the following: (a) for use by a First Nation [...] (b) for a water conservation objective; (c) for storage, if it is for the protection of the aquatic environment and for improving the availability of water to existing licence holders and registrants; (d) for any purpose, if, on or before the date this Order is filed under the Regulations Act, an application for the licence that is complete and complies with the Act has been filed with the Director.

Sections 6 (Oldman) and 8 (South Saskatchewan) repeat s. 4 for those basins; the Oldman list adds the Little Bow Project/Highwood Diversion and Pine Coulee projects (s. 6(1)(e), (f)). New registrations only on applications complete by the filing date (ss. 4(2), 6(2), 8(2)). The Oldman and South Saskatchewan basins are defined like the Bow (s. 1(e), (f)): groundwater not naturally flowing to or from the rivers is outside the reserved water. The order does not restrict transfers of existing allocations under Water Act s. 81. In-force date inferred from the consolidation date (current as of 2007-08-03); text re-read 2026-11-22.

Guide to Preparing a Complete Water Act Application for a Licence or an Approval

How a Water Act licence, amendment, renewal or transfer is applied for: through the department's online system, with the surface-water directive or the groundwater guide by source.

Environment and Protected Areas guide, 2024-05-22Alberta Environment and Protected AreasIn force 2024-05-22 (published)Read 2026-11-22

  • LicenceA licence is required for the diversion (the impoundment, storage, consumption, taking or removal of water for any purpose) of water. Applications for licences are to be submitted in the Digital Regulatory Assurance System (DRAS).
  • LicenceFor a water diversion application from a surface water source, follow the Surface Water Allocation Directive. For a water diversion application from a groundwater source, follow the Environment and Protected Areas guide to groundwater authorization.
  • TransfersA transfer of allocation allows allocated water to be transferred to a new location permanently or temporarily. A change in the point of diversion, the point of water use, or both can trigger the transfer provisions of the Water Act.
  • If the Water Source is GroundwaterApplications that are less than 3,650 cubic metres per year will require: a driller’s report; and a list of other users within a 1-mile (1.6 kilometre) radius

The Water (Ministerial) Regulation, Schedule 3, lists the diversions exempt from a licence (its own entry here, read 2026-11-22).

Water (Ministerial) Regulation

Lists the diversions of water that need no licence (Schedule 3), among them saline groundwater, fire fighting, roof rainwater used on its parcel, camps up to 2,500 m³ a year and small temporary uses; fresh water from a river, lake or well for a plant is not on the list.

Alta Reg 205/1998Minister responsible for the Water ActIn force 1999-01-01 (with the Water Act; not checked in this read)Version consolidation current as of 2026-10-29 (up to Alta Reg 264/2026)Read 2026-11-22

  • s. 5(1)A diversion of water or operation of a works described in Schedule 3 is exempt from the requirement for a licence.
  • Sch. 3 s. 1(e)a diversion of saline groundwater;
  • Sch. 3 s. 1(g)a diversion of water for the purposes of fire fighting;
  • Sch. 3 s. 1(g.1)a temporary diversion of water of up to 100 cubic metres per day per source of water for the purposes of fire prevention, firefighting training or spill training exercises, if (i) there is no adverse effect on (A) the aquatic environment, (B) a household user, licensee or traditional agricultural user, or (C) any parcel of land, [...]
  • Sch. 3 s. 1(b.1)a diversion of water from precipitation that is intercepted and captured by a roof and eavestrough system of a building, if the captured water is (i) either used immediately or stored in a container, tank or vessel that is separate from any other source of water, and (ii) used only within the boundaries of the parcel of land or property on which it is collected;

Schedule 3 s. 1 also exempts up to 2,500 m³ a year a camp (a), a manual-pump well (b), some dugouts (c), storm-pond and borrow-pit water under conditions (c.1, c.2), construction dewatering of 6 months or less (f.1) and some wetland and riparian work (j to m). Hydrostatic testing of pipelines follows a code of practice (s. 6). Read in full 2026-11-22.

Water Act

A licence is needed for any diversion of water unless the Act authorizes it otherwise (household use, a registration, an approval, or a diversion the regulations exempt), and the Director may stop accepting licence applications where no more water should be allocated.

RSA 2000 c W-3Legislature of AlbertaIn force 1999-01-01Version consolidation current as of 2026-03-11Read 2026-11-10

  • s. 49(1)Subject to subsection (2), no person shall (a) commence or continue a diversion of water for any purpose, or (b) operate a works, except pursuant to a licence unless it is otherwise authorized by this Act.
  • s. 49(2)A person who commences or continues the diversion of water or operates a works (a) for household purposes in accordance with section 21, (b) pursuant to a registration, (c) pursuant to an approval, (d) that is designated or is part of a class of diversions or works that is designated in the regulations as exempt from the requirement for a licence, or (e) [...] is not required to hold a licence for that diversion of water or operation of works.
  • s. 1(1)(x)“household purposes” means the use of a maximum of 1250 cubic metres of water per year per household for the purposes of human consumption, sanitation, fire prevention and watering animals, gardens, lawns and trees;
  • s. 53(1)If the Director is of the opinion that no further allocation of water should be made in a water management area or other geographical area considered appropriate by the Director or from a water body, the Director may decide that applications for licences are not to be accepted by the Director for a specified period of time.
  • s. 1(1)(fff)“water” means (i) all water on or under the surface of the ground, whether in liquid or solid state, and (ii) precipitation that is intercepted above the ground and captured by works;
  • s. 30(1)Licensees and traditional agriculture users have priority among themselves according to the priority number that has been assigned to the licence or registration.
  • s. 81(7)An application for a transfer of an allocation of water under a licence may be considered only if (a) the ability to transfer an allocation in the area of the Province referred to in the application has been authorized (i) in an applicable approved water management plan, or (ii) if there is no applicable approved water management plan, by an order of the Lieutenant Governor in Council, [...] and (c) the allocation of water to be transferred is held under a licence in good standing.
  • s. 82(7)(b)(i)the new licence that is issued in respect of the transferred allocation (i) must be given the same priority number as the licence from which the allocation was transferred
  • s. 83(1)[...] the Director may withhold up to 10% of an allocation of water under a licence that is being transferred.

Transfers of existing licensed allocations are under ss. 81 to 83 (s. 81 as amended 2025 c 27); the s. 81(7), 82(7), 83(1), 30(1) and 1(1)(fff) excerpts were read on 2026-11-22 in the consolidation current as of 2026-03-11. The 1999 commencement date was not checked in this read.

Historic resources

Historical Resources Act

The Minister may order a historic resources impact assessment for an activity likely to damage historic resources, and have other permits withheld until satisfied.

RSA 2000 c H-9, s. 37Legislature of AlbertaIn force RSA 2000; s. 37 amended 2020Version consolidation current as of 2022-11-16Read 2026-11-10

  • s. 37(2)When the Minister is of the opinion that any operation or activity that may be undertaken by any person will, or is likely to, result in the alteration, damage or destruction of historic resources, the Minister may order that person (a) to carry out an assessment to determine the effect of the proposed operation or activity on historic resources in the area where the operation or activity is carried on, [...]
  • s. 37(3) (partial)Notwithstanding anything in any other Act, when the Minister makes an order under subsection (2) the Minister may also require any municipality or other authority in Alberta, the issuance of whose licence, permit, consent or similar authorization is a condition precedent to the commencement or continuation of the operation or activity, to withhold or suspend the licence, permit, consent or other authorization until the Minister is satisfied [...]

Listing of Historic Resources: Instructions for Use

Says which projects must file a Historical Resources Act application whatever the Listing shows, including every project that needs AUC approval.

Listing of Historic Resources, Instructions for Use (Sept 2023)Government of Alberta (Historic Resources Management)In force 2023-09 (revised)Read 2026-11-10

  • p. 3The following types of projects always require the submission of an HR Application: [...] • projects that require approval by the Canadian Energy Regulator or Alberta Utilities Commission

Policy guidance, not legislation. The same list includes industrial facilities and water diversion projects.

Federal impact assessment

Beacon AI Centers Heartland Project: Notice of Early Decision with Reasons

The Agency decided no federal assessment was needed for the 920 MW Beacon Heartland plant (before the 2026 repeal).

IAAC Registry 90123Impact Assessment Agency of CanadaIn force decision 2026-03-09; notice 2026-03-10Read 2026-11-10

  • Notice of Early Decision with ReasonsOttawa — March 10, 2026 — The Impact Assessment Agency of Canada ( IAAC ) has conducted an assessment of the Beacon AI Centers Heartland Project (the project) and on March 9, 2026, decided at an early stage that no further assessment is required for the project proposed by Heartland Power (the proponent), located in Alberta.

Clean Electricity Regulations

Federal emission-intensity limit on fossil-fuel generating units of 25 MW or more connected to a NERC-standard electricity system: 65 t CO2/GWh for 2035 to 2049. Held in abeyance in Alberta (canada-alberta-implementation-agreement).

SOR/2024-263Governor in Council (Canadian Environmental Protection Act, 1999)In force registered 2024-12-17; the emission limit applies from 2035Version Justice Laws, current consolidationRead 2026-11-15

  • s. 5(1)(a), (c)the unit has an electricity generation capacity of at least 25 MW; ... the unit is connected, directly or indirectly, to an electricity system.
  • s. 2(1), electricity systemsubject to the standards of the North American Electric Reliability Corporation
  • s. 9(1)(a)65 tonnes of CO2 emissions per GWh for the 2035 to 2049 calendar years
  • s. 10(2)(a)January 1, 2035

Greenlight Electricity Centre Project: Notice of Early Decision with Reasons

The Agency decided no federal assessment was needed for the 1,864 MW Greenlight plant (before the 2026 repeal).

IAAC Registry 89790Impact Assessment Agency of CanadaIn force decision 2025-10-02; notice 2025-10-06Read 2026-11-10

  • Notice of Early Decision with ReasonsOttawa — October 6, 2025 — The Impact Assessment Agency of Canada ( IAAC ) has conducted an assessment of the Greenlight Electricity Centre Project (the project) and on October 2, 2025, decided at an early stage that no further assessment is required for the project proposed by Greenlight Electricity Centre Limited Partnership (the proponent), located in Alberta.

Impact Assessment Act

For a designated project, the Agency decides after the initial description whether a federal impact assessment is needed, within 180 days of posting that description.

S.C. 2019, c. 28, s. 1Parliament of Canada; administered by the Impact Assessment Agency of CanadaIn force 2019-08-28Version consolidation current to 2026-10-19Read 2026-11-10

  • 16(1)After posting a copy of the notice on the Internet site under subsection 15(3), the Agency must decide whether an impact assessment of the designated project is required.
  • 16(2.1)The Agency may decide that an impact assessment is required only if it is satisfied that the carrying out of the designated project may cause adverse effects within federal jurisdiction or direct or incidental adverse effects.
  • 18(1)If the Agency decides that an impact assessment of a designated project is required — and the Minister does not approve the substitution of a process under section 31 in respect of the designated project — the Agency must, within 180 days after the day on which it posts a copy of the description of the designated project under subsection 10(2), provide the proponent of that project with (a) a notice of the commencement of the impact assessment of the project that sets out the information or studies that the Agency requires from the proponent and considers necessary for the conduct of the impact assessment; and
  • 18(3)The Agency may, on request of any jurisdiction referred to in paragraphs (c) to (g) of the definition jurisdiction in section 2, extend the time limit referred to in subsection (1) by any period up to a maximum of 90 days, to allow it to cooperate with that jurisdiction with respect to the Agency’s obligations under subsection (1).

The 180-day limit is in s. 18(1), not s. 16; it can be extended by up to 90 days (s. 18(3)).

Implementation Agreement for the Canada-Alberta Memorandum of Understanding of November 27, 2025

Carbon pricing under TIER and the status of the federal Clean Electricity Regulations in Alberta: held in abeyance while the CER Reference is before the courts.

Implementation Agreement, 2026-05-15Government of Canada and Government of AlbertaIn force 2026-05-15Version Prime Minister of Canada backgrounder, 2026-05-15Read 2026-11-15

  • §2.1.1Canada will maintain the Clean Electricity Regulations (“CER”) in abeyance while the CER Reference is before the Alberta Court of Appeal and any subsequent appeal to the Supreme Court of Canada (“SCC”) proceeds.
  • §2.1.2Canada and Alberta will enter into negotiations towards an equivalency agreement on the CER under the Canadian Environmental Protection Act, 1999 to stand down the regulations in Alberta
  • §2.1.3Canada agrees to repeal the CER and Alberta agrees to maintain the carbon pricing framework defined in this agreement.

Physical Activities Regulations

The list of designated projects under the Impact Assessment Act; fossil-fuel power plants of 200 MW or more were on it until the items were repealed on 2026-09-03.

SOR/2019-285Governor in Council (Impact Assessment Act)In force 2019-08-28Version consolidation current to 2026-10-19, last amended 2026-09-03Read 2026-11-10

  • Schedule, Oil, Gas and Other Fossil Fuels (current consolidation)30 [Repealed, SOR/2026-185, s. 3] 31 [Repealed, SOR/2026-185, s. 3]
  • Schedule s. 30 (in force 2023-03-27 to 2026-09-02)The construction, operation, decommissioning and abandonment of a new fossil fuel-fired power generating facility with a production capacity of 200 MW or more.
  • Schedule s. 31 (in force 2023-03-27 to 2026-09-02)The expansion of an existing fossil fuel-fired power generating facility, if the expansion would result in an increase in production capacity of 50% or more and a total production capacity of 200 MW or more.

Regulations Amending the Physical Activities Regulations

Removed fossil-fuel power plants (new plants of 200 MW or more, and large expansions) from the federal designated-project list.

SOR/2026-185Governor in Council (Impact Assessment Act)In force 2026-09-03 (registered)Version Canada Gazette Part II, 2026-09-09Read 2026-11-10

  • s. 3Sections 30 to 33 of the schedule to the Regulations are repealed.
  • s. 6These Regulations come into force on the day on which they are registered.
  • Regulatory Impact Analysis Statementfossil fuel-fired power generating facilities would continue to be assessed under provincial processes

Grid connection (AESO)

Connection Process Performance Update (April 2026)

How long AESO connection stages actually take against their targets, for behind-the-fence and connection projects.

AESO Connection Process Performance Update, April 2026Alberta Electric System OperatorIn force report; data September 2023 to March 2026Version April 2026 (latest posted at 2026-11-10)Read 2026-11-10

  • Behind-the-fence projects (target / maximum / actual average weeks)Total Stages 0-2 24 46 75 Stage 3/4 26 52 89
  • Connection projects (target / maximum / actual average weeks)Total Stages 0-2 24 60 86 Stage 3 32 70 134
  • Table footnote*Actual average stage durations reflect the time it takes the AESO, the market participant and the applicable legal owners of transmission facilities to complete required deliverables.
  • Page 2As shown above, the vast majority of projects exceed the established targets and maximums set out in ID #2018-018T.

The Stages 0–2 totals are sums of per-stage averages, not an observed end-to-end average.

Guide to AESO Connection Requirements for Transmission-Connected Data Centres

Technical connection requirements the AESO applies to transmission-connected data centres of any size, such as ride-through, ramping and telemetry.

AESO data centre connection guide (2026-06-12)Alberta Electric System OperatorIn force guidance (binding through ISO rules, reliability standards and functional specifications)Version 2026-06-12Read 2026-11-10

  • 1. ApplicabilityThe AESO will review all transmission-connected data centre facilities, regardless of size, to determine whether the TCDC requirements and mitigations referred to in this guide are appropriate.
  • Executive SummaryThis guide should be read in conjunction with ISO rules, Alberta Reliability Standards and AESO Functional Specifications. In the event of a conflict, these authoritative documents take precedence.
  • 2. Definitions (Ramp30)This is the ramp that can typically be managed with reactive dispatching in normal operations and is 300 MW per 30 minutes (10 MW/min).

Does not mention tethered or bridged data centres or a 75 MW threshold; those are in the Data Centre Regulation.

Phase 2A: Large Load Integration – Bring Your Own Generation process

The AESO’s process for large loads that bring their own generation; Phase 1 allocated a 1,200 MW interim limit and Phase 2A was still being finalised.

AESO Engage, Phase 2A large load integrationAlberta Electric System OperatorIn force not final at the 2026-09-08 updateVersion update of 2026-09-08Read 2026-11-10

  • PurposeThe AESO rolled out Phase I of the Large Load Integration Program on June 4, 2025. Phase I included a 1,200 MW interim large load connection limit and a process for allocating that load among qualified project developers.
  • Stakeholder update, 2026-09-08While we had anticipated sharing the BYOG process and associated materials in August, we are still working to finalize the process , taking into account stakeholder feedback. You can expect these documents to be posted and application intake to begin this fall .

Data centres

AUC’s role in data centre projects (fact sheet)

Says the AUC does not approve data centres themselves, only the regulated utility facilities a data centre needs, with no separate category.

AUC data centre fact sheetAlberta Utilities CommissionIn force guidanceVersion undated; file dated 2026-08-17Read 2026-11-10

  • Does the AUC approve data centres?No. The AUC does not regulate data centres themselves.
  • Does the AUC approve data centres?If a data centre proposal requires the construction or operation of regulated utility facilities, those components require AUC approval.
  • Are data centre applications treated differently from other projects?No. There is no separate regulatory category for data centres under AUC legislation.

The AUC no longer serves this fact sheet at its own address (checked 2026-11-18) and its education library no longer lists it; the link is the Internet Archive copy of 2026-11-01, the same file read on 2026-11-10. The three excerpts are in it word for word.

Bill 42, Energy, Environment and Utilities Statutes Amendment Act, 2026

A government bill that would require an AUC approval for data centres of a prescribed maximum demand and let Cabinet make regulations on their construction and operation; as introduced it has no water or cooling provision.

Bill 42, 31st Legislature, 2nd Session (2026)Legislative Assembly of Alberta (Minister of Technology and Innovation)In force Not in force: first reading 2026-11-18; not passed when readVersion as introduced (first reading)Read 2026-11-22

  • s. 5(9), proposed HEEA s. 11.1(2)Subject to subsection (3), no person shall construct or operate a data centre unless the construction or operation, as the case may be, [...] (b) is approved by an order of the Commission, and (c) is in accordance with the regulations.
  • s. 5(9), proposed HEEA s. 11.1(5)(d)(i)The Lieutenant Governor in Council may make regulations [...] (d) for the purpose of subsection (2)(c), (i) respecting the construction or operation of a data centre,
  • s. 5(9), proposed HEEA s. 11.1(6)(b)A regulation made under subsection (5) may [...] (b) incorporate standards, methods or other rules set out in a document of a government or agency in relation to the matters referred to in that subsection,

Status read on the Assembly's bill page on 2026-11-22: first reading passed 2026-11-18 (afternoon); no later stage listed. The text as introduced was searched for water and cooling and has neither word; any cooling-water standard would come in regulations made under the proposed s. 11.1(5), none of which is published.

Data Centre Regulation

Defines a large data centre as 75 MW or more of maximum demand from the transmission system, lets the AESO lower that, count linked sites as one and set connection criteria, and puts tethered data centres first in the AESO’s queue.

Alta Reg 117/2026Minister responsible for the Electric Utilities Act (s. 41.01)In force 2026-06-09 (filed that day; no commencement section, so in force on filing under the Regulations Act s. 2(2))Version as filed 2026-06-09, published in the Alberta Gazette Part II of 2026-06-30; King’s Printer extract current as of 2026-06-09Read 2026-11-10

  • s. 1(2)(c)(c) “demand” means the rate of electric energy that may be consumed by a data centre from the transmission system instantaneously, measured in megawatts;
  • s. 2(2)The Independent System Operator may establish and apply a lower maximum demand threshold for the purpose of determining whether data centres are, or proposed data centres will be, large data centres if the Independent System Operator determines that a lower threshold is required to [...]
  • s. 3For the purposes of this Regulation, the Independent System Operator may treat 2 or more data centres as a single data centre if (a) in the opinion of the Independent System Operator, the data centres are or will be physically or operationally integrated and are or will be located on the same parcel or adjacent parcels of land, and (b) one or more of the following circumstances exists:
  • s. 2(1)For the purposes of this Regulation, a data centre is a “large data centre” if the data centre has, or in the case of a proposed data centre will have, a maximum demand directly from the transmission system equal to or greater than (a) 75 megawatts, or (b) a lower maximum demand threshold established under subsection (2).
  • s. 1(2)(b) and (f)(b) “bridged data centre” means a tethered data centre that is provided with system access service in accordance with section 9; [...] (f) “tethered data centre” means a large data centre, or a proposed large data centre, that has been designated as a tethered data centre under section 5(1);
  • s. 6The Independent System Operator must prioritize the processing of a system access service request for a tethered data centre over the processing of a system access service request for a large data centre that is not a tethered data centre or a proposed large data centre that is not a tethered data centre.
  • s. 7(1)The Independent System Operator may establish criteria that a person requesting system access service or a modification to system access service for a large data centre, or a proposed large data centre, must meet to the satisfaction of the Independent System Operator, including criteria relating to (a) site control for the site where the large data centre is or will be located, (b) municipal zoning approvals, (c) financing, and (d) the issuance of permits or water licences.
  • s. 9(5)System access service or modified system access service may be provided to a bridged data centre for a maximum of 3 years from when it is first provided, or for a shorter period as determined under subsection (4)(a), and may be [...]

Corrections to the law-firm summaries: the test is maximum demand directly from the transmission system (the text never says demand transmission service); no clause is labelled anti-avoidance, the nearest is the s. 3 aggregation power; tethered means the request is tied to new, expanded or underused generation or storage at least equal to the data centre’s maximum demand (s. 5), not necessarily owned by it; bridged is a tethered data centre served before its generation, so s. 6 ranks tethered ahead of non-tethered, not ahead of bridged. Bridged data centres are curtailed first in a supply shortfall (s. 10). The regulation expires 2035-05-31 (s. 12). Demand counts only what may be drawn from the transmission system (s. 1(2)(c)), so a data centre with no transmission connection has none; the regulation does not say how on-site generation behind a transmission connection is counted. In force 2026-06-09: the Alberta Gazette Part II of 2026-06-30 records it as filed June 9, 2026, it has no commencement section, and the Regulations Act s. 2(2) brings a regulation into force on the day it is filed.

Electric Utilities Act

Gives the Minister power to make regulations on data centres (the source of the Data Centre Regulation) and the AESO power to make rules about them.

SA 2003 c E-5.1, ss. 20(1)(i.1), 41.01Legislature of AlbertaIn force s. 41.01 added by SA 2025 c 26Version consolidation current as of 2026-02-06Read 2026-11-10

  • s. 41.01The Minister may make regulations respecting data centres, including regulations (a) defining “data centre”; (b) respecting classes of data centres; (c) respecting the provision of system access service to data centres; (d) respecting load management, load shedding and the consumption of electricity by data centres;
  • s. 20(1)(i.1)(i.1) data centres;

Data centre levy

Alberta Corporate Tax Act, Part 9.1: Data Centre Levy

A yearly levy on the computing equipment of data centres with 75 MW or more of electricity capacity: up to 2% on a share of the equipment cost, weighted by how much of their electricity comes from the grid.

RSA 2000 c A-15, Part 9.1 (ss. 92.2 to 92.92)Legislature of Alberta; levy paid to the Provincial Minister (Treasury Board and Finance)In force 2026-01-01Version consolidation current as of 2026-03-26; added by SA 2025 c 20 (Bill 12), amended by SA 2026 c 3 (Bill 17)Read 2026-11-10

  • s. 92.3(1)Subject to subsection (6) and any regulations made under section 92.91(1)(c), an operator shall pay a levy to the Provincial Minister on the computing equipment of each data centre described in subsection (3) and each co-location facility described in subsection (4) for each calendar year as required by this Part.
  • s. 92.3(3)(a)(3) The levy imposed under subsection (1) is payable on the computing equipment of a data centre, referred to in this subsection as the “particular data centre”, for a calendar year where (a) the electricity capacity of the particular data centre is 75 MW or greater at any time in the calendar year,
  • s. 92.3(7)The levy payable under subsection (1) in respect of a data centre or a co-location facility for a calendar year is the amount determined by the formula (E + F) x R [...] E is the product of 45% and the total of the cost of computing equipment of the data centre or co-location facility that is available for use at the end of the calendar year that is less than 4 years old in age at the end of the calendar year; [...] (((G – N)/T) x 0.02) + ((N/T) x 0.01)
  • s. 92.3(7), G and TG is the total electricity received by the data centre or co-location facility from the power grid in the calendar year; T is the total of all amounts each of which is an amount of electricity received by the data centre or co-location facility in the calendar year from any source, including from electricity generated by the operator of the data centre or the person responsible for the co-location facility;
  • s. 92.2(1)(p)(p) “power grid” means all transmission facilities and all electric distribution systems in Alberta that are interconnected, including a transmission facility or electric distribution system within the service area of the City of Medicine Hat or a subsidiary of that City;
  • s. 92.5(1)An operator liable to pay a levy under this Part for a calendar year, on or before the end of the 14th calendar month after the end of the calendar year, shall (a) file a return with the Provincial Minister in the prescribed form and manner containing the prescribed information and showing the amount of levy payable by the operator for the calendar year, and (b) pay to the Provincial Minister the amount of levy payable by the operator for the calendar year.

Not a separate act or regulation. The rate R is 2% on grid electricity, 1% on grid electricity matched by new capacity or self-generation, and nothing on electricity not received from the grid; E is 45% of the cost of equipment under four years old and F 15% of older equipment. The first levy year is 2026, on equipment in use at year end; the return and payment are due by the end of the 14th month after the year. The levy is creditable against Alberta corporate tax (ss. 25.05 to 25.07). “Electricity capacity” is not defined in Part 9.1 (s. 92.2 has no such definition); the permit path reads it as the data centre’s load. N, the electricity charged at 1%, is grid electricity delivered under a new power capacity agreement or a self-generation arrangement, both of which deliver through the power grid (s. 92.2(1)(m), (r)). Summaries of a flat 2% (or 1% if self-generating) from 2026-12-31 simplify this.

Reclamation security

Decision 30261-D02-2026: Greenlight Electricity Centre Project

Approval of the 1,864 MW Greenlight plant, with reclamation security by letters of credit stepping up every five years from commercial operation to the full updated estimate by year 20.

AUC Decision 30261-D02-2026Alberta Utilities CommissionIn force 2026-06-25 (reasons and conditions; approved in 30261-D01-2026 on 2026-06-19)Read 2026-11-10

  • ¶48The total estimated cost to complete demolition and reclamation of the project is approximately $30.54 million (in 2025 dollars), inclusive of demolition, site grading, revegetation, contractor overhead, engineering, and contingency costs.
  • ¶56 condition kOn the fifth anniversary of the date of commercial operation and every five years after that until year 20, Greenlight Electricity Centre GP Ltd. shall file a confirmation with the Commission that reclamation security in the form of one or more irrevocable standby letters of credit with automatic renewal from a qualified institution (as defined in the Alberta Treasury Board and Finance Guidelines for Letters of Credit: Qualified Financial Institutions) has been provided to the registered owner, or registered owners, of the land under the surface lease, in accordance with an updated third-party cost estimate.
  • ¶56 condition lOn the 20th anniversary of the date of commercial operation, Greenlight Electricity Centre GP Ltd. shall file confirmation with the Commission that the full amount of reclamation security has been posted, in accordance with an updated third-party cost estimate.

Decision 30518-D01-2026: Beacon AI Centers – Heartland Project Thermal Power Plant

Approval of a 920 MW gas-engine plant serving a co-located data centre, with reclamation security of 5% of the estimate in year one rising annually to the full amount by year 20.

AUC Decision 30518-D01-2026Alberta Utilities CommissionIn force 2026-10-23 (approved with conditions)Read 2026-11-10

  • ¶7The power plant will consist of a natural gas-fired generating facility with a nominal generating capability of 920 megawatts (MW). It will include 200 natural gas engines, each with a nominal capability of approximately 4.6 MW, arranged in 40 modules, together with associated equipment and ancillary facilities.
  • ¶123 condition gBy the end of the first year of operation, Northbridge Power GPC Inc. shall provide the reclamation security in an amount equal to five per cent of the most recent third-party decommissioning and reclamation cost estimate. The security must increase annually and equal the full amount of the most recent third-party decommissioning and reclamation cost estimate by the end of year 20 of operation.
  • ¶123 condition hOn the fifth anniversary of the date the power plant commences operation and every five years thereafter for the duration of the project’s operational life, Northbridge Power GPC Inc. shall obtain an updated third-party decommissioning and reclamation cost estimate that does not deduct anticipated salvage or scrap value.

Municipal land use

Municipal Government Act

Every municipality has a land use bylaw, and a development permit must issue for a permitted use that conforms to it; discretionary uses are decided case by case. An AUC, AER or NRCB approval prevails over municipal plans, bylaws and permit decisions, and the municipality must approve a consistent application to the extent it complies with that approval (s. 619).

RSA 2000 c M-26, ss. 619, 640, 642Legislature of AlbertaIn force RSA 2000Version consolidation current as of 2026-09-01Read 2026-11-10

  • s. 619(1)A licence, permit, approval or other authorization granted by the NRCB, ERCB, AER, AEUB or AUC prevails, in accordance with this section, over any statutory plan, land use bylaw, subdivision decision or development decision by a subdivision authority, development authority, subdivision and development appeal board, or the Land and Property Rights Tribunal or any other authorization under this Part.
  • s. 619(2)When an application is received by a municipality for a statutory plan amendment, land use bylaw amendment, subdivision approval, development permit or other authorization under this Part and the application is consistent with a licence, permit, approval or other authorization granted by the NRCB, ERCB, AER, AEUB or AUC, the municipality must approve the application to the extent that it complies with the licence, permit, approval or other authorization granted under subsection (1).
  • s. 619(3)(a)(3) An approval of a statutory plan amendment or land use bylaw amendment under subsection (2) (a) must be granted within 90 days after the application or a longer time agreed on by the applicant and the municipality, and
  • s. 640(1)Every municipality must pass a land use bylaw.
  • s. 642(1)When a person applies for a development permit in respect of a development provided for by a land use bylaw pursuant to section 640(2)(b)(i), the development authority must, if the application otherwise conforms to the land use bylaw and is complete in accordance with section 683.1, issue a development permit with or without conditions as provided for in the land use bylaw.

Section 619 reaches what an AUC, AER or NRCB authorization covers, such as an AUC power plant approval; the AUC says it does not regulate data centres themselves (AUC data centre fact sheet), so the data-centre building rests on the municipal bylaw alone. A municipal hearing on a consistent application may not reopen matters the regulator decided, except to decide whether a plan or bylaw amendment is needed (s. 619(4)); a refusal or a missed 90-day deadline can be appealed to the Land and Property Rights Tribunal (s. 619(5)).

Sour gas setbacks

Directive 056: Energy Development Applications and Schedules

The AER’s application rules for wells, pipelines and facilities, including minimum distances from sour pipelines and sour facilities to dwellings, country residential clusters, towns and public buildings, set by the H2S release volume level.

AER Directive 056Alberta Energy RegulatorIn force 2026-10-01Version edition of 2026-10-01 (replaces 2026-03-31)Read 2026-11-10

  • 6.5.2 Setback Requirements for Select PipelinesThere are specific setback distances between sour natural gas and oil effluent pipelines and pipelines associated with geothermal energy or brine-hosted mineral development with H2S content greater than10 mol/kmol and permanent dwellings, unrestricted country developments, urban centres, or public facilities.
  • Table 6 (sour pipelines, p. 81; level, H2S release volume in m3, minimum distance, read across)1 <300 Pipeline right-of-way 2 >300 to <2000 0.1 km to individual permanent dwellings and unrestricted country developments 0.5 km to urban centres or public facilities 3 >2000 to <6000 0.1 km to individual permanent dwellings up to 8 dwellings per quarter section 0.5 km to unrestricted country developments 1.5 km to urban centres or public facilities 4 >6000 As specified by the AER, but not less than level 3
  • 5.6.9, requirement 39The applicant must meet the applicable setback requirements in table 5 based on the calculated H2S release volume for pipelines associated with the proposed facility.
  • Table 5 (category C, D or E facilities, p. 72; levels 1 and 4, read across)1 <300 Lease boundary [...] 4 >6000 As specified by the AER, but not less than those given in level 3
  • Glossary, public facilityA public building, such as a hospital, rural school, or major recreational facility, situated outside of an urban centre that can accommodate more than 50 individuals or that requires additional transportation to be provided during an evacuation.
  • 3.2.2, requirement 18(h)h) discussion of the potential restrictions regarding developing lands adjacent to the proposed development, such as setbacks (section 2.110 of the OGCR and the Subdivision and Development Regulation; e.g., future surface improvements within 100 m of the wellhead may be subject to county/municipal development restrictions)

Table 5 gives facilities the same level 2 and 3 distances as Table 6; Table 10 (p. 117) sets them for sour wells. The app reads the H2S release volume and emergency planning level that the AER pipeline data publishes for each sour segment (about 1,980 of 5,226 sour gas segments carry one) and shows the Table 6 distances for that level next to each nearby line; where a segment carries no published level, it says so rather than assuming one. Sour-gas plants (sulphur recovery, acid gas flaring or injection) are listed by distance; their facility levels are not in the public data used here. The tables run from the sour facility to the categories they name; data centres and industrial buildings are not named among them. Restrictions on new development near existing sour facilities sit in the Subdivision and Development Regulation and OGCR s. 2.110, which are not in this library.

Each document sits under its main topic. Dates: in force as stated by the publisher; read is the day the text was checked for this app. Statutes and regulations from Alberta King’s Printer and the federal Justice Laws site; AUC, AESO and IAAC documents from their own sites. Data & sources lists the datasets.