Models

Every calculation, and how far to trust it

22 models turn public records into the figures PatchWatt shows. Each says what it is for, what goes in, how it works, and how far it has been checked against real outcomes. Screening arithmetic, not an engineer’s, lender’s or reserves evaluator’s model. Every default it starts from, with its source, is on the Assumptions panel; what changed and when is on Changes.

01Cooling water for the sized plant

Applies a published method or path

The range of water a gas-fired plant of the case's size would withdraw and consume for cooling, by cooling system, beside what is licensed near the point.

Inputs
Plant MW, run hours and availability from the case (overrides included), the plant type, and the US NREL water factors for gas combined cycle by cooling system.
Method
Energy a year (MW × run hours × availability, no ambient derate) times the lowest and highest withdrawal and consumption factors in NREL/TP-6A20-50900 Tables 2 and 3, gallons converted to m³; simple-cycle and engine plants have no factor in the source and are stated as not known.
Checks
Tests hold the arithmetic to the factors, the range to their low and high, the run-hours override to the range, and the page, Compare and the water_licences_nearby tool to the same figures.
Used by
Place page and site report Water and cooling section, recipe reports, Compare water rows; water_licences_nearby tool (API, MCP, Ask AI).

02Cost of power (levelized)

Back-tested against outcomes it did not see

What a MWh from a gas plant at a site costs over its life, in constant 2025 C$, with connections and carbon.

Inputs
Plant (capital, O&M, heat rate, build years), load and run hours, gas price, carbon price, gas lateral and grid tie distances, cost of capital and life.
Method
Capital restated to 2025 C$ by Statistics Canada indexes, interest during construction added, recovered at the real rate over the life; fixed and variable O&M, fuel at the heat rate, TIER carbon and the gas and grid connections added per MWh.
Checks
Capital at the default scored against 15 Canadian gas new builds, each left out of its own range: mean absolute error 21%, inside the stated range 15 of 15 (run of 2026-11-16, before the capital changes of 11-17 and 11-19). Four filed Alberta projects scored on heat rate, capital and build period.
Recorded in: Capital back-test and filed-project back-test, 16 November 2026
Used by
Place page sizing section, Compare, site reports; plant_cost tool (API, MCP, Ask AI).

03Cost sensitivity (tornado) and scenarios

Arithmetic and logic checks only

Which inputs move the cost of power or a return most, and the low, central and high cases.

Inputs
The case shown, and a low and high value for each input from published or measured ranges.
Method
Each input is moved alone to its low and high value and the same case re-run; named scenarios move several together.
Checks
Tests hold each swing to the case it starts from and the order of the bars to the size of the swing; the ranges themselves come from published or measured figures, each sourced.
Used by
Sizing and finance sections, well economics, Compare; plant_cost and well_economics tools.

04Plant capital figures

Back-tested against outcomes it did not see

The capital a plant type costs at a size, and the published spread around it.

Inputs
Filed and agency capital figures for Canadian gas plants, each with its year, scope and page.
Method
Each figure restated by its plant type's index, raised by the measured post-2022 step where it was struck before 2023, scaled to the size by the six-tenths rule; the median is the default and the extremes the range.
Checks
Leave-one-out back-test over 15 filed Canadian new builds (run of 2026-11-16). The engine step was measured on one plant's two estimates and is an open item.
Recorded in: Capital back-test, 16 November 2026; cost-model notes on the engine step, 17 November 2026
Used by
Sizing section, capital table, finance; plant_cost tool.

05Interest during construction and debt sizing

Checked against published real cases

The financing cost while the plant is built, and how much debt the cash flow carries.

Inputs
Build years, cost of capital, debt rate and share, tenor, coverage target, revenue type.
Method
Interest during construction from an even spend over the build years; debt is the lesser of the gearing cap and what the coverage target allows, repaid as a level annuity or sculpted.
Checks
Debt share at Greenlight's contracted coverage 63–65% against about 60% in the owner's release; equity and project IRR order checked over 1,368 cases.
Recorded in: Finance case matrix, 18 November 2026
Used by
Finance section, sizing (capital with interest); project_finance tool.

06Hourly dispatch against pool prices

Checked against published real cases

When a plant would run against Alberta's hourly pool price, and what it would earn.

Inputs
Hourly pool prices, monthly gas prices, heat rate, variable O&M, carbon, trading charge, loss factor, availability; operating reserve prices when on.
Method
The Market Surveillance Administrator's net-revenue method: run each hour the price covers the short-run cost plus a hurdle; reserves earn in hours the plant is off.
Checks
Reproduces the MSA's 2025 net revenue for its reference plants (combined cycle +1.8%, simple cycle +7.3%) on its own inputs; capacity factor and captured price inside real Alberta units' range 7 of 7 years.
Recorded in: Finance case matrix and the dispatch validation view, 18 November 2026
Used by
Finance section and returns headline; plant_cost tool.

07Forward power and gas case

Not validated: a proxy or an assumption

Returns on today's traded forwards rather than on past years.

Inputs
TC Energy's and the MSA's published forward prices (power and AECO gas) and each past year's hourly price shape.
Method
Each past year's hourly shape is shifted so its mean meets the forward for the year; low and high cases scale by the spread of past years. Not a forecast.
Checks
Forwards are traded prices, not outcomes; the case has not been scored against later years.
Used by
Finance section headline (forward case first).

08Project finance and returns

Checked against published real cases

Project and equity returns of a gas plant, as a range over past years and the forward case.

Inputs
Dispatch results by year, capital, O&M, tax classes, debt terms, carbon case, revenue type (merchant, toll, self-supply).
Method
Annual nominal cash flows over the life with capital cost allowance by class and losses carried forward; IRR and NPV for each past year's prices held over the life, plus the forward case.
Checks
1,368 cases with 0 invariant violations; MSA years, the Greenlight toll, debt and tax checked against published figures within stated bands.
Recorded in: Finance case matrix and the real-case checks, 17 to 19 November 2026
Used by
Finance section, place reports, Compare; plant_cost and project_finance tools.

09Gas price scenarios

Applies a published method or path

Gas prices over a plant's life, from the Canadian public outlooks.

Inputs
Canada Energy Regulator Energy Futures and AER ST98 scenarios (latest editions); MSA and TC Energy forwards; realized AB-NIT prices.
Method
Published scenarios as printed, deflated to 2025 C$; no price of PatchWatt's own. Realized prices so far are shown beside each scenario's figure for this year.
Checks
Each scenario is the publisher's; the realized-price table shows how far this year's scenario sits from what has traded.
Used by
Sizing and finance sections, market pages; plant_cost tool.

10TIER carbon path and levelized carbon

Applies a published method or path

The carbon cost or credit of a plant over its life under Alberta's TIER regulation.

Inputs
The TIER price path (Canada–Alberta agreement, 2026-05-15), the benchmark, the plant's emission intensity, the credit-market share.
Method
Obligation above the benchmark met partly with credits at the market price and partly at the fund price; levelized over the life at the real rate.
Checks
The path is as published to 2035 and by its stated escalator to 2040; a test holds the sizing and outlook copies equal.
Used by
Sizing, finance, emissions; plant_cost tool.

11Heat rate, gas burn and plant size

Back-tested against outcomes it did not see

How much gas a plant of a given size burns, and the plant size a load needs.

Inputs
Load, run hours, availability, heat rate (filed or measured), site temperature and altitude, heating value of the gas.
Method
Gas need from the heat rate on an energy basis, converted at the local heating value; derated for site heat and altitude; units sized with spare capacity.
Checks
Fleet back-test of heat rate against Alberta plants' measured figures (GHGRP CO2 over AESO output), each left out; Fox Creek's filed 8.42 against the default 8.52 GJ/MWh.
Recorded in: Fleet back-test and filed-project back-test, 16 November 2026
Used by
Sizing section, gas supply comparison; plant_cost tool.

12Gas and grid connections, tolls and the transmission tariff

Back-tested against outcomes it did not see

The cost to connect a plant to gas and the grid, gas transport, and what self-supply saves.

Inputs
Distance to the nearest sales line and substation or line in the voltage band, plant size, NGTL tolls, the AESO tariff.
Method
Lateral cost per inch-km sized to the gas; grid tie at the AESO's direct-connection cost plus measured line cost per km; NGTL toll stack on contract demand; tariff band from fully avoided to charged on gross load.
Checks
Grid cost scored against 16 AESO connection estimates with a stated circuit, each left out: inside the stated range 15 of 16; the point error is large (median absolute 72%) because the AESO figures cover only the transmission owner's part. Lateral cost from 10 NGTL laterals.
Recorded in: Grid connection back-test
Used by
Sizing section, Compare, finance (self-supply); plant_cost tool.

13Spark spread and implied market heat rate

Applies a published method or path

What a MWh sold at the pool price earned over its gas, month by month.

Inputs
Monthly pool price, AB-NIT gas price, a heat rate, TIER.
Method
Spark spread = pool price less heat rate times gas price; implied heat rate = pool price over gas price.
Checks
Arithmetic on published prices.
Used by
Market pages (power and gas prices).

14Catchment supply decline and its back-test

Back-tested against outcomes it did not see

The gas an area or a plant's catchment would deliver over the next years.

Inputs
Reported production of the area's wells and facilities (Petrinex), recent well count.
Method
A fitted decline for each recent well and for the older base, resampled for the spread; a path with wells added at the recent pace; the central path between them. Each area's own back-test beside the provincial range.
Checks
Every method forecast from past dates over 97 Alberta areas of 25 km and compared with what the facilities reported 1, 2 and 3 years later; the range printed is where 8 in 10 back-tests fell.
Recorded in: Supply back-test, rebuilt on each data refresh
Used by
Place page gas supply, plant catchments, well sets.

15Type curves and EUR

Back-tested against outcomes it did not see

A well set's typical production profile and 30-year volume, stated as public benchmarks state it.

Inputs
Monthly production of the set's recent horizontal wells (Petrinex), laterals (AER ST37).
Method
Wells aligned on months on production, P10/P50/P90 per month, a modified-hyperbolic Arps fit; each well's EUR by the method a hindcast chose (own fit blended with the cohort's decline).
Checks
Hindcast over 1,094 Alberta horizontal gas wells cut at 6, 12 and 18 months; method and blend chosen by a rule fixed before the run.
Recorded in: EUR hindcast back-test, 18 November 2026
Used by
Well review pages, well sets, wells report; well_economics tool.

16Single-well economics

Checked against published real cases

NPV, IRR and payback of a well like the set's, gross and before tax.

Inputs
The central production profile, gas and liquids prices, capital, operating cost, Crown royalty, NGTL fuel and surcharge, abandonment.
Method
Monthly cash flow to the economic limit; royalty under Alberta's Modernized Royalty Framework; tornado and scenarios over the inputs.
Checks
Costs, royalty rates and volumes compared with operators' disclosures for named well sets; differences listed by cause.
Recorded in: Well economics real-case checks, 17 to 19 November 2026
Used by
Well review economics panel, wells report; well_economics tool.

17Well cost formula

Checked against published real cases

A well's capital from its depth and lateral length, and the play's operating cost.

Inputs
The set's median true vertical depth and lateral; operators' disclosed per-well costs; the producing formation.
Method
Least-squares line C$M = a + b × depth + c × lateral over the disclosures; the play read from Petrinex pool names (Duvernay by basin outline).
Checks
Against operators' own figures: Fox Creek C$11.1M vs Whitecap's C$10.0M (+11%), Baytex Pembina design −9%.
Recorded in: Well economics real-case checks and the play cost benchmark, 19 November 2026
Used by
Well economics panel and report; well_economics tool.

18Screening grid rules

Not validated: a proxy or an assumption

Which 5 km cells of Alberta meet the thresholds a reader sets.

Inputs
The province grid (gas, pipes, grid, ground, water, protected areas per cell) and the reader's thresholds.
Method
Cells are filtered by each threshold, never scored or ranked.
Checks
A filter on the reader's own thresholds; nothing to fit. The grid's build is checked on each refresh.
Used by
Map screening mode.

19Abandonment and reclamation liability (Directive 011)

Applies a published method or path

A dollar range for closing a licensee's or an area's inactive wells and sites.

Inputs
Well licences by status, depth and completion (Petrinex), township cost areas, Directive 011 rates.
Method
AER Directive 011 regional abandonment and reclamation costs applied well by well at each well's depth and area.
Checks
The AER's published rates and maps, read by a pipeline step; the AER's own per-licensee figures are not public to compare with.
Used by
Operator pages, well sets, place liability section.

20Crown land value

Applies a published method or path

What Crown petroleum and natural gas rights near a place have sold for.

Inputs
Alberta's public offering results (bonus, area, zone interval, date).
Method
Medians of $/ha of sold parcels by zone and year, beside the province; comparable sales within a window.
Checks
Descriptive medians of recorded sales.
Used by
Land and market pages, place land section.

21Building counts and the noise limit

Not validated: a proxy or an assumption

How many buildings are near a site and the night sound limit at them under AUC Rule 012.

Inputs
Overture building footprints (a pinned release) on a grid, OpenStreetMap building tags.
Method
Buildings counted within set distances of the point; density category from buildings per quarter section; Rule 012's basic sound level by category.
Checks
Counts are footprints, not dwellings; the rule measures from the property line, this from the point. Stated on the page.
Used by
Place page ground section, noise.

22Connectivity: fibre presence proxy and latency estimate

Not validated: a proxy or an assumption

Whether high-capacity transport is reported near a site, funded broadband projects nearby, and how far Calgary and Edmonton are in distance and indicative fibre round trip.

Inputs
ISED National Broadband Data: hexes reporting high-capacity transport services, funded project layers, community points. Light in fibre at two thirds of c; route factor 1.2 to 1.86 (Bozkurt et al. 2018, US long-haul fibre).
Method
Distance and direction to the nearest transport hex centre and counts within 25 km; funded project hexes by programme; straight-line km to each city and round trip = 2 × km × route factor × 5.0 µs per km. No route geometry exists publicly.
Checks
A proxy: a hex says a provider reports service there, not where a cable runs. The round trip is an estimate of propagation only, from US route factors, not a measured Alberta latency.
Used by
Place page Connectivity section, site report, Compare, power pre-feasibility and shortlist recipes, tools connectivity_nearby and ground_and_permits.